INVESTOR | SUBJECT OF THE CONTRACT |
![]() |
Cleaning and painting of Hala Walcownia Walcówki at ArcelorMittal Poland S.A. O / Sosnowiec
General overhaul of Blast Furnace No. 2 at ArcelorMittal Poland S.A. Branch in Dąbrowa Górnicza.
Ceramic ladle repairs at ArcelorMittal Poland S.A. Branch in Dąbrowa Górnicza.
Renovation works of facilities and equipment at ArcelorMittal Poland S.A. Dąbrowa Górnicza branch in the industry: thermal insulation, anti-corrosion, roofing works, ceramics. |
![]() |
Anticorrosion ISChK in the area of Koksownia Przyjaźń
Ceramic repairs of ISChK chambers and dust collectors at Koksownia Przyjaźń Dąbrowa Górnicza.
Corrosion protection of PT 18-32 crane at Koksownia Przyjaźń Dąbrowa Górnicza.
Renovation of the facade of the Wagon Generator Hall at Koksownia Przyjaźń Dąbrowa Górnicza.
Renovation of chemical resistant protections at the sewage treatment plant at Koksownia Przyjaźń in Dąbrowa Górnicza. |
![]() |
Thermal insulation of Electrofilters No. 5 and 6 on the SA HUTNICZE PRZEDSIĘBIORSTWA REMONTOWE sinter belt No. 3 at ArcelorMittal Poland S.A. Branch in |
![]() |
Thermal insulation of the absorber and pipelines Ø 9000 mm at the Flue Gas Desulphurization Installation at Jaworzno III Power Plant for Termoizolacja S.A. O / Oświęcim (currently KAEFER S.A.) |
![]() |
Renovation of facilities and equipment for EC Nowa Sp. Tauron ArcelorMittal Energy Holding z o.o. (currently TAMEH Polska Sp.z o.o.) in the industry: thermal insulation, anti-corrosion, roofing works, chemically resistant rubber linings, subject to UDT. |
![]() |
Renovation of the hall for the preparation of foundry sets on the premises of The Łabędy S.A. Hut in Gliwice – anti-corrosion. Corrosion protection of hangars construction at Katowice International Airport in Pyrzowice. |
![]() |
Refurbishment of furnaces No. 1 and 4 at the Press Branch of Kuźni Batory Sp. z o.o. – general contracting. |
![]() |
Construction of furnace chambers for burning biomass – ceramic works. |
![]() |
Execution of thermo modernization of the building of the production hall. |
![]() |
Renovation of the heat treatment furnace with the sliding shaft “Seco-Warwick” at the Rolling Mill Department. |